The tech giant may be required to post over $7 billion in security for a new data center after a Wisconsin regulator upheld strict credit rules, a move that could add significant costs to its AI expansion plans.

Text size
Background

Oracle may be required to post more than $7 billion in collateral to secure power for a massive new data center in Wisconsin after state regulators declined to relax their credit requirements. The decision presents a significant financial hurdle for a project central to the company's artificial intelligence strategy, the Financial Times reported on Monday.

Regulator Upholds Credit Rules

The Public Service Commission of Wisconsin affirmed a rule that impacts the local utility, We Energies. The regulation requires any large customer with a Standard & Poor's credit rating below single A minus to post collateral, in the form of cash or a letter of credit, to cover the cost of new infrastructure built to serve them.

According to the FT, Oracle currently holds a triple B rating, which is two notches below the required threshold. The collateral amount is calculated based on the value of the power plants and transmission lines needed for the nearly one-gigawatt data center. Securing a letter of credit for this amount could cost Oracle more than $100 million annually.

Sample IUX Markets – In-articleAd

Implications for AI Expansion

The data center in Port Washington, Wisconsin, is a critical component of Oracle's plan to fulfill a reported $300 billion contract to provide computing power to OpenAI. This potential collateral requirement adds to growing financial pressures on the company, including rising debt and rapid cash expenditure tied to its ambitious AI build-out.

Oracle had petitioned a county judge last month to have the rule removed or to allow We Energies to waive the requirement. The company argued the rule imposes "burdensome financing costs" and could discourage future investment in the state, per the FT. However, a representative for the commission told the FT it had declined to act on the petition. Oracle expressed hope that the commission would reconsider, citing the economic benefits of the $15 billion project.