Energy Transfer Pipeline for Oracle AI Data Center in New Mexico Delayed to 2027

ENTHMSVIIDZHZH-TWJAKOHI
Aug 14, 20262 min read
Energy Transfer Pipeline for Oracle AI Data Center in New Mexico Delayed to 2027
Text size
Background

The in-service date for a new natural gas pipeline in New Mexico, designed to supply an Oracle Corp. data center, has been pushed back by more than five months. The project, operated by an Energy Transfer LP subsidiary, is now expected to begin service in early 2027, a delay that could impact the timeline for bringing the new technology facility online.

Timeline Shift

Transwestern Pipeline, a subsidiary of Energy Transfer, stated in a regulatory filing on Friday that its "Green Chile Project" will now enter service on February 1, 2027. The pipeline was previously scheduled to begin operations on August 15, 2026.

The project is designed to deliver up to 400,000 dekatherms per day of new firm transportation capacity. This natural gas supply is slated for a new artificial intelligence and data center facility being developed by Oracle in Doña Ana County, New Mexico.

Regulatory Background

The delay was disclosed in a submission to the Federal Energy Regulatory Commission (FERC). According to the document, the update was provided in response to a FERC data request dated August 11, 2026.

Sample IUX Markets – In-articleAd

Transwestern Pipeline initially submitted the project for approval with FERC on January 29, 2026. The company is seeking authorization to construct and operate the pipeline facilities under its existing blanket certificate.

Context for Investors

This delay highlights the potential for infrastructure bottlenecks as technology companies race to build out power-intensive AI data centers. The surging demand for electricity and reliable energy sources like natural gas is a critical factor for the expansion of cloud computing and AI services.

While the financial impact on a large operator like Energy Transfer may be limited, the revised timeline is more significant for Oracle. Delays in securing necessary power infrastructure can affect the operational launch of data centers, which are crucial for competing in the rapidly growing AI market.